Vermonter Upgrade To Continue This Summer

E-mail Print PDF

The New England Central Railroad has finished three quarters of the Vermonter route upgrade, part of the ARRA stimulus fund.

All 18 trainloads of rail has been laid while ties, surfacing and bridge work will continue south of White River Junction this spring and summer to instal 50,000 ties, redo 25 switches and strengthen and speed up 15 bridges.

At certain times the work will cause delay's to Amtrak's Vermonter by up to 30 minutes.  This is because after new ties and ballast have been installed, the track must settle a bit and slow orders are imposed until it does.

When finished the project will result in a schedule within Vermont that is 27 minutes faster.  Massachusetts and Connecticut have their own projects (Massachusetts will be done in 2013, Connecticut in 2016) that will bring futher speed improvements en-route to New York.

The project has received a "no findings" status from the federal audit, which is good.

The goal is to finish work by September 12th, after which the track geometry car will visit and measure and certify to work, with speeds raised by the fall time change.

The project is on track to be the first "high-speed" stimulus fund project completed.

 

 
getOnBoard

E-mail Updates

Be in the know!
Enter your e-mail for occasional updates.

Donate!

Click here to give by credit card (via PayPal) or check. Send checks to PO Box 75, Putney VT 05346
Thank You!

Volunteer!

You can contribute! Call Christopher Parker: (802) 579-3394
Overview. Sign Up Form
Train Host Program
Our Special 'Wish List'

Be Heard!

Your voice is critical to making sure that elected officials and the public know rail's importance.
Educate Your Legislator
Community Outreach
Letters to the Editor

Facebook Image

Upcoming Events

New Amtrak Service?

The following Amtrak improvements in Vermont are under discussion but take money and your political support.  Please sign up at left for e-mail updates, write to your representatives and a letter to the editor and consider volunteering to help make these enhancements reality.

Burlington - Middlebury to New York
Vermonter to Montreal
Multiple frequencies from Rutland, Bennington to New York
"Knowlege Corridor:" faster, more frequent service to New York from White River Jc, Bellows Falls & Brattleboro
Boston - Burlington - Montreal high speed rail

Environmental Benefits of Rail

 

44% of greenhouse gasses in Vermont are produced by transportation (nationally, it's 28%).  If we are serious about the environment we have to change transportation.

Shipping by rail instead of truck reduces pollution (on average) by two-thirds, noise by one half, uses only 29% of the fuel and produces only 23% as much greenhouse gasses.  Freight Rail Carbon Calculator

The U.S. transportation system is 96% petroleum dependent, accounts for 71% of the country’s oil use, and consumes 25% of the world’s net output. 

Passenger trains are 20-40% more efficient.  But consider: if the train is already going there, the carbon footprint of you  riding it is *zero* !  

Rail facilitates better land use, which may make the biggest difference.